SUMMARY

• Broad site experience including strong experience in Instrumentation, Oil&Gas, Petrochemical, Energetics (0.4kV, 6 kV, 10kV, 35kV), Mining and Heavy Industry sector

• Experience in Maintenance, Construction and Commissioning. Good Communication and Proven Mentoring Skills

• Knowledge of commissioning related engineering drawing e.g. PFD, P&ID, D&ID and Electrical Single Line Diagram etc.

• Ability to adapt to new situations and technologies due to solid understand across broad engineering fields from High Voltage to Controls

• Experienced in PTW, Isolations & SIMOPS during commissioning and start-up phases

• Good knowledge (commissioning and calibration) of all types of instruments and valves, including Nucleonic, F&G systems, Yokogawa marshaling and field equipment

• Hazardous Areas: – Ex and dusty areas

• Advanced computer skills (Word, Excel, Outlook, Adobe Acrobat, AutoCAD, 3D MAX, Step 7-SIEMENS, Easy Plant, EDMS)

• User skills in ICSS Yokogawa and ABB, Allen Bradley

• I can use all types of calibration instruments, “Hart communicator”, “Fluke” etc.

• Commissioning and maintenance of low-current networks and equipment (security and fire systems; notification and fire extinguisher systems; CCTV).

• Problem solving experienced

• Stress resistant

• Able to self-learning

EDUCATION

Innovative University of Eurasia. Graduated In 2004

Qualification: Bachelor Degree in Electrical Engineering. Specialty: The electrical supply of industrial enterprises.

JOB HISTORY

12.2023 – till now “Arctic SPG2”

Position: Instrumentation Expert

Project: Arctic LNG 2

Commissioning and start up of Gas turbine «Harbine»Close collaboration with construction, Field Engineering departments as a Client. Peroration of the weekly plans, participating in the weekly plan meetings, walk downs, issuing and clarification of the punch lists. Collaboration with warehouse department, help to contractors to identify, find out and receive materials, tools and drawings. Motivation and managing of work progress, work with Smart Plant. Issuing of the PRs, MRs, writing technical queries and reports. Monitor and assist in Vendor activities.

08.2022 – 11.2023 “Novus Bolashak”

Position: I&C 3GP SC Lead, Utility South Area– Process. Object: Tengizchevroil

Project: FGP Pre Commissioning and Commissioning

Close collaboration with construction, Field Engineering departments and Client. Peroration of the weekly plans, participating in the weekly plan meetings, walk downs, issuing and clarification of the punch lists. Collaboration with warehouse department, help to technicians to identify, find out and receive materials, tools and drawings. Motivation and managing of work progress, work with Smart Plant. Issuing of the PRs, MRs, writing technical queries and reports. Reporting to area coordinator. Monitor and assist in Vendor activities.

11.2021 – 08.2022 “Novus Bolashak”

Position: I&C Commissioning Engineer Object: Tengizchevroil

Project: FGP Pre Commissioning and Commissioning

Close collaboration with construction, Field Engineering departments and Client. Checking installation of the equipment, according to the manuals and norms. Participating in the QA/QC inspections, walk downs, weekly meetings issuing and clarification of the punch lists. Collaboration with warehouse department, help to technicians to identify, find out and receive materials, tools and drawings. Motivation and managing of work progress, work with Smart Plant. Issuing of the PRs, MRs, writing technical queries and reports. Monitor and assist in Vendor activities.

12.2018 – 10.2021 “WOOD KSS” (WOOD GROUP)

Position: E&I Construction Lead. Object: Tengizchevroil

Project: FGP – MAC (Main Automation Contractor)

Motivation and managing of work progress. Participate in the walk downs, weekly meetings, issuing and clarification of the punch lists, work with design and estimate documentation. Daily reporting to Area Coordinator, issuing of the PRs, MRs, writing technical queries and reports. Monitor and assist in Vendor activities

11.2018 – 11.2019 “WOOD KSS” (WOOD GROUP)

Position: E&I Construction Supervisor. Object: Tengizchevroil

Project: FGP - MAC

Pulling, measuring(continuity, megger, ductor tests) and termination of cables, installation and termination of transmitters and other electrical and instrument equipment according to manuals and norms. Closing of punches, modification of installed equipment marshaling and PAS cabinets. Participate in the QA/QC inspections, walk downs, permit meetings issuing and clarification of the punch lists. Motivation and managing subcontractors work progress, work with design and estimate documentation. Daily reporting to construction team leader, issuing of the PRs, writing technical queries and reports. Adjusting and troubleshooting of the field equipment. Monitor and assist in Vendor activities

11.2016 – 11.2018 “South Tambey LNG”

Position: Commissioning Instrument Supervisor. Object: “Yamal LNG”

Project: Pre-Commissioning, Commissioning and start up.

Close collaboration with construction, Field Engineering departments and Client. Checking installation of the equipment, according the manuals and norms. Participated in the QA/QC inspections, walk downs, issuing and clarification of the punch lists. Collaboration with warehouse department, help subcontractor to identify, find out and receive materials and tools. Motivation and managing subcontractors work progress, work with design and estimate documentation. Participating in progress meetings, daily reporting to commissioning team leader, issuing of the PRs, writing technical queries and reports, Supervising and acceptance of the loop tests, repairing, adjusting and troubleshooting of the field equipment. Monitor and assist in Vendor activities

02.2015 – 09.2016 - “KazMinerals” via “Bolashak Atyrau”

Position: Electrical &Instrumentation Commissioning Engineer.

Object: “Bozshakol Copper Project” Mining and beneficiation complex.

Project: Pre-Commissioning, Commissioning and start up.

Control and organization of work of contractors, work with project design and estimate documentation. QC inspections.

Participating in progress meetings, daily reporting to commissioning team leader, issuing of the PRs

Supervising and acceptance of the loop tests, repairing and adjusting of the field instruments and electrical equipment (6-35kV) and troubleshooting.

Monitor and assist in Vendor activities.

Areas of responsibility – Primary Crusher, OLC and Reclaim the first objects were commissioned and handed over for maintenance

02.2014 -11.2014 - “SIBUR” via “Anotech Energy”

Position: Instrumentation Commissioning Engineer. Object: "IKRA" Project. Polyvinyl Chloride (PVC) Integrated Plant, Nizhniy Novgorod city, Russia

Project: Pre-Commissioning, Commissioning and start up.

Control and organization of work of contractors, working with project design and estimate documentation.

Progress monitoring, strictly observance of schedules and work plans QC inspections. Providing and acceptance of the loop tests, repairing and adjusting of the field instruments.

Supervising and troubleshooting as a duty instrumentation engineer. Monitor and assist in Vendor activities.

Area of responsibility – PVC area, pre-commissioning, commissioning and start up

05.2013 - 02.2014 - “Kazakhstan Aluminum Smelter”

Position: Maintenance Instrument Engineer.

Maintenance of instruments and programs SIMATIC - Step 7 and WinCC (SIEMENS), HMI devices, programmable logic controllers (SIEMNS), user skills in the SCADA system.

05.2012 – 01.2013 - “Sapsan”

Position: Duty Electrical Technician. Object: Plant of complex preparation of oil and gas “Tengischevroil”

Operative maintenance and repair of electrical equipment, pumps

Project: “Turnaround 2012” as an Instrumentation QA/QC inspector

03.2011 – 05.2012 - “PSN KAZSTROY”

Position: Commissioning Instrumentation Technician Object: Plant of complex preparation of oil and gas «Bolashak» (Karabatan)

Adjustment and check of the Fire & Gas systems (adjustment and repair of shut-off valves, temperature and pressure transmitters, loop check of smoke, optical and heat line detectors, flame and gas detectors, adjustment of a communication between HVAC and F&G systems, carrying out of cause effect). Adjustment and check process instruments (LT, TT, FT and other).

Adjustment and calibration of the valves and transmitters.

QC inspections and adjustment of the field instruments. Areas: Oil, Sulphur, KIB

12.2010 -02.2011 - "Montazhspecstroy"

Position: Construction Instrument Engineer, fire and gas systems. Object: Plant of complex preparation of oil and gas «Bolashak» (Karabatan)

Organization of work, working with project design and estimate documentation. QC inspection and checking of the contractors

Area of responsibility - Oil

02.2007 – 03.2010 - "Intel Dom".

Position: Electrical and low voltage system Supervisor.

Organization of work, working with design and estimate documentation.

Installation, commissioning, and adjustment of the security, fire alarm water and gas fire extinguishing systems, CCTV, low-voltage and medium -voltage equipment, ventilation and air-conditioning systems