WORK SUMMARY

30 years of experience in Pre-Commissioning, Commissioning, Start-up, Normal operation and Shut down activities of LNG and LPG plants.

Coordinating, Managing and Supervising work activities for Process Train Plant Shutdown and Start Up such as developing/executing Shutdown and Start Up Sequences and Equipment shutdown preparation, and till hand over for Maintenance program

Commissioning & Start up Specialist Operation in Yemen LNG 2010

HAZOP Team for Process Train & Utilities Plants, Badak LNG

Train G Commissioning and Start up, 1992, Responsible for starting up Process Train covering CO2 Removal, Dehydration/Mercury Removal, Fractionation, Refrigeration and Liquefaction units and Utilities Units TECHNICAL SKILLS

Budgeting

Business Plan

Employee Relation

Business Process Design

Job Evaluation

Manpower Planning

Organizational Development

Performance Management

Recruitment and Selection Process

Reward Management

Occupational Health and Industrial Hygiene Management

Ability to work independently.

Proven leadership skills and ability to motivate

Highly organized and efficient

WORK HISTORY

Manager Utilities

Project: Badak LNG, Bontang - Indonesia

Period: From 28/11/2016 – 20/05/2017

Job Description:

Managing all activities related to Utilities Area to ensure the achievement of safe and reliable LNG / LPG production target and ensure that all activities are carried out professionally and efficiently. Manager Trains ABCD

Project: Badak LNG, Bontang - Indonesia

Period: From 03/04/2015 – 27/11/2016

Job Description:

Managing all activities related to Process Train ABCD to ensure the achievement of safe and reliable LNG / LPG production target and ensure that all activities are carried out professionally and efficiently. Shift Coordinator

Project: Badak LNG, Bontang - Indonesia

Period: From 14/05/2014 – 02/04/2015

Job Description:

Responsible to manage and coordinated LNG and LPG plant operations in shift basis, consist of eight unit LNG Train (CO2 Removal, Dehydration and Mercury Removal, Fractionation/Distillation, Refrigeration and Liquefaction Plants), Utilities Plant (Steam Generation, Power Generation, Nitrogen Plant, Compressed Air Plant, Cooling Water Plant, Water Treatment Plant), Storage & Loading (LNG/LPG Tank, LNG/LPG Loading Dock, Knock Out Drums, Condensate Stabilizer, LPG Plant, Blowdown System) as well as Fire & Safety.

Coordinate whole plant to ensure the achievement of LNG, LPG and condensate productions target on quality, on quantity and on time safely, reliably and efficiently perform troubleshoot operation conditions anomaly and give direction to Supervisor to take decision. Operation and Liquefaction Specialist

Project: PT Saipem Indonesia

Period: From May 2013 - 2014

Job Description:

Front End Engineering Design Floating Liquefied Natural Gas of Abadi Filed Development Project capacity 2.5 MTPA. Client: Inpex Corporation, Pte Ltd

Preparing deliverables for project

Review documents from other disciplines which related to LNG operations and liquefaction process

Participate and advise on HAZIP meeting

Q-Captain for operation flawless project deliverable by providing mitigation action to prevent flaw during project phases and ensure those mitigation actions to be amended into relevant deliverables

Contribute and provide technical advice related to LNG operation and liquefaction process

Participate and advise for PID’s review and HOZOP meeting Internal Auditor, Audit & Compliance

Project: Badak LNG, Bontang - Indonesia

Period: From 21/03/2013 – 30/04/2013

Job Description:

Responsible for Facilitating the development and implementation of the SHEQ programs, reviewing the SHEQ MS Manual and SHEQ MS SOP (Standard Operating Procedure), providing advices, consultation and monitoring of the implementation of the SHEQ program and related work activities and disseminating the best practices found in each element of the SHEQ MS Manual and SHEQ MS SOP. Report all incidents of accident / injury / illness to the Manager as soon as possible; Review accident report from first-line supervisor / engineers. Check the performance of SHE-Q with first-line Supervisor / engineer and report to Manager. Operation Specialist

Project: Badak LNG, Bontang - Indonesia

Period: From 11/04/2011 – 20/03/2013

Job Description:

Coordinate and manages the Training Project in Badak LNG learning Center covering Proposal, Syllabus, Schedule, Modules, Learning Method, Instructor, Assessment, Facilities and Accommodation

Support technical services provided for the clients

Manage the Commissioning and Start Up Assistance Organization and Personal. Start Up Coordinator

Project: Yemen LNG, Yemen

Period: From 2010 - 2011

Job Description:

Coordinated the on-shift operation pre-commissioning, commissioning for starting up Process Train covering CO2 Removal, Dehydration/Mercury Removal, Fractionation, Refrigeration and Liquefaction, Utilities Units.

Coordinated the on-shift operation pre-commissioning, commissioning for starting up Blowdown system Shutdown Coordinator

Project: Badak LNG, Bontang - Indonesia

Period: From 07/04/2010 – 10/04/2011

Job Description:

Coordinated all activities on-daily operation to maintain good Thermal Efficiency, Product Quality and Environment Program

Coordinate all preparation of Start Up and Shutdown Activities with all related parties. Supervisor Process Shift

Project: Badak LNG, Bontang - Indonesia

Period: From 30/07/2001 – 06/04/2010

Job Description:

Coordinate operations of two unit LNG trains during 8 hours shift working to ensure the achievement of LNG and LPG production targets which are on quality, on quantity and on time in accordance with the requirements of safety, reliability and efficiency and ensure all plant facilities functioning properly and professionally executed.

Maintain good coordination and communication with other sections to minimize impact of changes in shared resources

DCS Retrofit Project Coordinator

Project: Badak LNG, Bontang - Indonesia

Period: From 2000 - 2001

Job Description:

Coordinated all activities of DCS Retrofit Project in Utilities and Process Plant, such as ensuring the project to be completed in timely manner and all facilities are in good working.

Proposed the modification of control system from analog to DCS system.

Prepared training module for operator in DCS system operation. Lead/Panel Operator Utilities & Process

Project: Badak LNG, Bontang - Indonesia

Period: From 17/06/1998 – 30/07/2000

Job Description:

Responsible for coordinating between Main Panel Operator and Field Operator, safely, efficiently and professional to ensure LNG & LPG production achievement and ensure all facilities working properly.

Monitoring and analyzing and problems solving. Recorded log-sheets and reported daily reports to Supervisor for plant activities. Used and understood all activities and procedures to prepare, start-up, shutdown, and isolate equipment. Executed emergency drill. Identified possible maintenance and / or safety issues.

Operator, Process Train A/B/C/D

Project: Operation Department, PT Badak NGL, Bontang - East Kalimantan Period: From 10/08/1987 – 16/06/1998

Job Description:

Responsible for operating at Process Train area on Plant-4 Refrigeration Unit MCR and Propane.

Monitoring and analyzing and problems solving. Recorded log-sheets and reported daily reports to Main panel operator and Supervisor for plant activities. Used and understood all activities and procedures to prepare, start-up, shutdown, and isolate equipment. Executed emergency drill. Identified possible maintenance and / or safety issues.

EDUCATION

Bachelor of Chemical Engineering, Sekolah Tinggi Teknologi Industri Bontang, East Kalimantan – Indonesia (2009)

Oil & Gas Academy, Sekolah Tinggi Energi & Mineral, Cepu, Middle Java – Indonesia (2000)

Senior High School, SMA Negeri Sukabumi, Indonesia (1984)

Junior High School, SMP PGRI Sukabumi, Indonesia (1981)

Elementary School, SD Negeri I Mukuh, Indonesia (1975) TRAINING/CERTIFICATES

2016 Effective Cost Management

2016 Incident Investigation & Action Tracking

2015 Advanced Budgeting & Cost Control

2014 Training LNG Spill Rescue & Fire Fighting

2014 Training Manager Development Program

2013 QMS ISO 9001 Lead Auditor

2013 Training Need Analysis

2012 Contract & Capital Project Management

2011 AFE Project Management & Contract

2011 Steering Committee ISO 14001 & 9001

2011 WS. Fireye Flame Scanner

2011 Reliability Engineering & Management

2010 APCI Seminar LNG Owner USA

2009 Work Permit and Receiver Certificate

2008 Supervisory LNG Indonesia

2008 SHE-Q Ms Work Permit

2007 Chloride Industrial UPS

2006 P3S : Gas Processing

2005 Centum CS3000 Operation Engineering & Maintenance 2005 W.S Operator Development Prog (ODP)

2005 Power & Steam Management System

2004 Leadership and Powership

2002 Automatic Control System

2001 Safety Training Observation Program (STOP)

2001 ISO 9001:2000 Awareness for All Employee

2001 Electrical System

2000 ISO 14001 Awareness EMS

2000 Oil And Gas Academy Level II : Gas Processing 1998 DCS XL Fundamental

1996 Project Management Professional (PMP)

1996 Fire/Safety Refreshing

1993 Refinery Operation & Economics Basic

1992 Basic Processing Engineering Course Gas Level-I 1991 4-KT Governor System

1991 Fire Safety & Security

1990 Basic Processing Engineering Course Gas Preparation 1989 Steam Trap Monitoring