Luca Iacoponi
Project Controls Manager – PCM
Mail: **************@******.**
Phone: +62-811-******* (WA)
Location: Surabaya – East Java – Indonesia
Birth Date: 28th January 1966
Civil Status: Married
WORK EXPERIENCE
Consultant Project Controls & Administration Surabaya, Indonesia
Aksay Industrial Park LLP
07/2023 – 01/2024
Project Control consultancy for 14 companies present in Aksay Industrial Park:
Profit & Loss for all companies; Initial Budget for all companies; Costs Project Report for Production; Cash In-out 6 months look ahead; Cash Flow (Weekly and Monthly); Personnel Units Rate, Labor Cost; Production Report in Weekly and Monthly base; Supervision and guidelines of Planning Department.
Deputy General Director Aksay, West Kazakhstan
Aksay Industrial Park LLP
09/2014 – 04/2023
Director of General Services for the Industrial Park (Project Control & Administration)
Director of HR Department; Director of Project Control Department; Director of Account department; Responsible of Budget for 12 companies present in the Industrial Park; Responsible of Profit & Loss preparation (quarterly) for 12 companies present in the Industrial Park
Project Controls Manager Karimun Island Fabrication Yard, Indonesia
Saipem S.p.A.
01/2010 – 07/2014
Head of Project Controls Department
PCON General Procedure preparation for Yard Start activities (in details Cost Control, Project Planning, Risk Control, Client Cost Planning & Monitoring, Progress Management Third Party Manpower, Document Control); Planning and Progress Report System for Projects Overall (EPC) and relative Fabrication activities; Evaluation and Finalization of the Budget’s Yard Costs for each Area/Buildings to identify the depreciation costs rate. Establishment of Planning Fabrication School (two months of training - theory & practice activities) for local resources and integration of the students in the Project Planning. Management of Projects Cost with development of Budget, Cost Report and relative PSR for each Project. Development of new system reporting for Fabrication Cost to give proper feedback at Estimating & Proposal Saipem Office for Commercial Tender. Development of new Yard Cost Report to monitor & analyze monthly the Yard running costs to give proper feedback at the Yard Management for internal spending review.
Projects:
Gorgon Projects (Chevron Australia - Marine Operation Platform & Jetty Head) – Project Value 37.000.000 USD
Al Wasit Project (Saudi Aramco – Tie in Platforms) – Project Value 86.000.000 USD
Iraq Crude Oil Export Expansion Project (ICOEEP) Phase 2 (CMMP) EPC Works – Project Value 47.000.000 USD
Construction of Fabrication Yars – Saipem S.p.A. – Project Value 500.000.000 USD
Project Controls Manager Atyrau, Kazakhstan
Saipem S.p.A.
03/2007 – 12/2009
Head of Project Controls Department
Planning & Cost Control for Saipem Kazakhstan Branch. Planning & Cost Control Management for the Kashagan AGIP KCO Oil & Gas Project (Trunk Line Kashagan Project – Piles & Flare Kashagan Island Project). Responsible for Costs, Planning and Document Control for the new incoming Projects. Development Cost control Procedure, Cost Report and relative PSR for both of Projects Trunk Line Kashagan Project – Piles & Flare Kashagan Island Project).
Project Value: 850.000.000 USD
Project Controls Manager Atyrau, Kazakhstan
Bonatti S.p.A.
01/2005 – 02/2009
Country Project Controls Manager
Planning & Cost Control for Bonatti Kazakhstan. Construction of Main Pipe Rack in Karabatan Field - Atyrau with set up of Baseline Schedule and Progress Database (AGIP KCO). Budget and Cost Report preparation for Main Pipe Rack in Karabatan Field; Planning Progress monitoring of several Wells Head with relative Pipeline in Karachaganak Field – Aksay. Responsible for Planning & Reporting for Shut Down activities in KPC & Unit 2 Plant - Karachaganak Field. Budget and Cost Report preparation for Shut Down Karachaganak Field (KPO)
Planner Manager Butrio (UD), Italy
Danieli S.p.A.
06/2004 – 12/2004
Planner Manager & Team Leader
Baseline EPC Project Schedule development and relative Progress Measurement Report; Material Planning; Engineering Planning; Construction planning; Pre-Commissioning and Commissioning Planning; Development of monthly progress report; Development of Weekly Report
Project: Construction of Steel Plant for Saudi Arabia Government = Value 125.000.000 USD
Planner Manager Aksay - Kazakhstan
Rina Industry S.r.l.
01/2004 – 05/2004
Planner Manager & Reporting Leader
Developed a procedure for the data management coming from welding tests; Development of control system for the NDT (MPI, PWHT, X-Ray, UT) report statistic; Statistic report of Welding activities; Weekly & Monthly report; Progress report
Project: Re-Start Phase of Train A, B, C and Unit 2 – Karachaganak Field
Planner & Costs Manager Pointe Noire – Republique of Congo
Nuovo Pignone S.p.A.
04/2002 – 12/2003
Planning & Cost Management Leader
Consumption materials and spare parts planning for the maintenance activities; Materials management monitoring; Budget preparation for Maintenance activities to be submitted through Cost Report in monthly base - Monthly analysis and Trend Deviation versus Eni Congo - Development baseline multidiscipline schedule and progress monitoring for the Plant; Development budget and Cost Report for the project; Budget preparation and Maintenance Cost Report in monthly base; Weekly & Monthly report; Progress report
Project: Construction & Operation of the Gas Power Plant of Djeno (ENI Congo) -Project Value: 2.000.000 USD
Planner & Maintenance Manager La Spezia - Italy
Zancolli S.p.A.
01/1994 – 03/2002
Planner & Production Manager
Development Production System for Tire Plant; Material Supply for Production Chain; Planning Annual Maintenance Production Machines; Planning Annual Spare Parts for Production Machines; Annual Budget Preparation and Monthly Reporting Productivity submission to General Direction; Production Monitoring & Evaluation of Productivity
Planner Vimodrone (MI) - Italy
Nuova Cimimontubi S.p.A.
06/1988 – 12/2001
Construction and Plant Planner
Development Baseline & S-Curve for the Project; Weekly & Monthly report; Development of 6 weeks of look ahead activities; Progress report; Data Collection from Supervision Team for Invoices Report.
Assigned at following Projects on site from 1989 to 2001.
Power Plant: Construction and modernization of new Coal Transport Facility - La Spezia - Project Value: 850.000 USD
Refinery Plant - Project: Shut-down activities in Sarras Sarroch Refinery (CA) – Italy - Project Value: 150.000 USD
Project: Construction of a Steel Plant Mobarakeh - Isfahan – Republic of Iran - - Project Value: 75.000.000 USD
Junior Planner Genova - Italy
SerGenova S.p.A.
01/1988 – 05/1988
Construction Planner
Weekly & Monthly report; Controlling of Baseline & S-Curve for the Project - Progress report
Power Plant - Project: Construction of a Power Plant in Tobruk – Libya
Technical Skills:
General Management, Project Management, Project Controls Management, Planning & Reporting, Cost & Budgeting, Team Coordination, Profit & Loss Management; Analytical Skills; Oil & Gas, Construction & Fabrication Projects
Computer Skills:
COMPUTER SKILLS
MS Office: Excel, Word, Outlook, PowerPoint; Primavera P3 & P6; Microsoft Project; SAP; Super Project Planning; Artemis
Certification & Course:
2011 - Project Management in Primavera P6 Rel. 7 – Primavera University – Singapore
2011 - Administration in Primavera P6 and P6 Web Access Rel. 7 – Primavera University – Singapore
1993 - Planning Production Tire – Good Year Italia S.p.A. (Milan – Italy)
1992 - Tire Vulcanization Machines Maintenance – Michelin Italiana S.p.A. (Rome - Italy)
1988 - Course Artemis 2000 Program – Nuova Cimimontubi S.p.A. Head Quarter (Milan – Italy)
1988 - Technical Planning Course – SERGENOVA (Genova - Italy)
Academic Profile:
Bachelor’s degree in mechanical engineering