Post Job Free
Sign in

Project Manager Solar Energy

Location:
Rochester, MN
Posted:
October 26, 2024

Contact this candidate

Resume:

Hicham Ounasser

757-***-****

******.********@*****.***

SUMMARY:

● 19+ years of solar energy and wind turbine construction/site management.

● Advanced construction knowledge, concrete finishing and testing, foundation knowledge and the ability to read construction electrical drawing and blueprints.

● Managed between 40 to 500 field contractors, electricians, and different constructions crews.

● Managed multiple sites on same time.

● Extensive experience managing the construction of Solar Farm.

● Motivated and positive attitude.

● Commission, Troubleshooting

PROFESSIONAL EXPERIENCE

03/2022- present

Borrego solar energy

Site Mnager/Project manager

Lead and overseeing all construction budget of 100 MW solar farm 02/2016- 03/2022

MW Group /Signal energy

Chandler AZ

Construction Manager

Lead and overseeing day to day operation for multiple Solar Farm projects . Responsible for organizing, motivating, and leading the operations team as well as the Safety, Quality, Efficiency, and ultimately the Customer Experience 03/2015-12/2015

Blattner Energy

Waynsboro GA

Superintended

● Develop detailed Project Contract status reports

● Coordinate with Project Superintendent in development of a project site logistics plan

● Oversee the pay request process

● Monitor project costs and Job Cost Report

● monitor training of all staff personnel

● Monitor project labor

● Review and approve material, forming system and equipment needs

● Assist Estimating in bidding projects

● Lead the project's quality process

● Develop, schedule and lead project close-out processes 08/2014 – 03/2015

Aeolus Energy

Michigan and Texas Regions

Construction Site Supervisor

● Managing the daily task for QA/QC, Maintenance and end of warranty.

● Managed 150 field contractors.

● Manage wind farm construction from Foundation, erection, power cable termination, QA/QC, and commissioning troubleshooting.

● MHI 2.4MW Gulf Wind TX and NORDEX 117

● Responsible for all mechanical, electrical task and QA/QC.

● Used my understanding of Electrical Design, hydraulic and electrical pitch system, service maintenance, ABB and Inga team Converter, changing Gen bearing, tower and hub torques. 02/2012 – 08/2014

Upwind Solutions

Multiple Markets

Field Services Engineer

● Finished End of warranty and walk down,165 Tower Blue Creek OH

● Troubleshooting 18 GE 1.5 in Fenner NY

● Tower Inspection .180 Tower of V82 IN Fowler IN

● OM Support for 50 G87 in NEW HARVEST IA

● Install SCADA for 25 GE Turbines In twin Falls Idaho

● OM Support for 12 GE 1.5 MW And 10 V47 in New York

● OM Support for 44 Turbine G87 in Sand Bluff TX

● QA/QC and walk down with the customer (Enel) for GE1.6 IN west Kansas

● Troubleshooting 165 turbines of G90 Blue Creek OH

● QA, QC of 85 SIEMENS 2.3 in morning light IA.

● Commissioning 50 DEWIND 92 in GUYMON OK

● Troubleshooting 45 GAMESA, HARDSCRABLE NY

● Troubleshooting 20 Clippers 2.5MW NASHVILE KS

● Troubleshooting 44 GAMESA G87 Sand Bluff TX

● Lead commissioning and troubleshooting 50 WTG G87 in Tehachapi, CA 01/2011 – 02/2012

Repower Energy

Canada and Michigan

Construction Site Manager

● Responsible for 250-300 field contractors, electricians, and different constructions crews for Repower Energy.

● Manage all operations and maintenance activities and supervise all personnel working on the project including leads, technicians and field staff on the assigned wind farm.

● Responsible for Logistic,Erection, Mechanical completion, Electrical completion,walk down, Commission and Final walk down to sign each turbine to the customer (Saint Robert in Quebec and stone corner in Cadillac Michigan).

2007 - 2011

Evolution Energy Group

Lead Construction Field Technician

Projects Included:

NORDEX in Cedar Creek, Colorado

● Finish electrical wiring for Nacelle Commissioning 8 Turbines Buffalo Ridge 2 GAMESA South Dakota

● Finishing Punch list and Final completion the turbine, walk down with customer Gamesa Lucas Riddge1 and 2, Shenandoah, PA

● QA/QC and Inspection for 65 Turbine G83 AND 54 Turbine G87

● QA/QC and inspection 50 Turbines G87

Nordic Wind Power Idaho Market

● Troubleshooting all electrical and mechanical problem of Nordic 1 MW Siemens Windy Flats, Goldendale, WA

● Commission 50+ Siemens 2.3 MW

● Commissioning & troubleshooting of Siemens 2.3 MW wind turbines in Oregon Market.

● Experienced in blades calibration, adjustments and change-outs of yaw motors/pitch systems. Familiarized with bearings and generator alignments and ABB converter.

● Grounding, Leveling, Offload, and Erection.

General Electric 1.5MW, Lamar, CO

● Changing double Bearing, grounding ring and generator alignment for 12 turbines Suzlon Cassia Wind Farm, Idaho and Oregon

● Commissioning and troubleshooting for 80+ SUZLON S-88 wind turbines rated at 2.1 MW.

● Experienced in blades calibration, adjustments and change-outs of yaw motors/pitch motors/pitch systems.

● Familiarized with bearings, and generator alignments.

● Provide technical support.

1998 – 2007

D.L. Aerotechnogie

Lead Quality Supervisor

● QA/QC, Control and training new employers. (Airbus aircraft Manufacturer) EDUCATION:

Certified six sigma green and black belt (2015)

ECOLE HASSANIA in Casablanca

Engineering Degree in science

Bachelor degree in Mathematic

I.S.T.A in Morocco

Technician in Design

TRAINING:

TRACTEL, TSL, High Torque certified, Confined Space, CPR, AED and Fall Protection Electrical Safety: NFPA 70E Arc Flash Training and OSHA 10H 1.5 MW GE Commission certified.