Post Job Free
Sign in

Technical Proposal Project Engineer

Location:
Bengaluru, Karnataka, India
Posted:
August 04, 2024

Contact this candidate

Resume:

RESUME TECHNICAL PROPOSAL

RESUME C.Kumaresan Page 1 of 3

● Name : C.Kumaresan.

C Licence No : 51954 (Tamilnadu

Electrical Licensing Board)

Father’s Name : S.Chinnaraj

Date of Birth : 30th July 1977

Educational Qualification : B.E (Electrical & Electronics) – 1999. Govt.College of Engineering, Tirunelveli.

Address for Communication : C.Kumaresan,

89 A, PillayarKovil Street,

Gudalur,

Theni – 625 518 :

Phone : 787*******

E Mail : ad7qwh@r.postjobfree.com

Nationality : Indian

Marital Status : Married

Experience: 20 + Years in EHV & HV Substation and Transmission Line projects . execution and Maintenance.

My relevant previous experience is as follows:

Manager, Renfra Energy India Pvt Ltd., Tenkasi

Mar’2024 to Till Now

● Manager,JSW Renew Energy Ltd.,(HINPA Incorporation) Tuticorin Jan’2022 to Feb’2024

● Manager, SRS Engineering Enterprises, Tirunelveli Jan 2020 to Dec' 2021

● Manager, PRV Constructions Pvt. Ltd.,Chennai

Dec 2017 to Dec 2019

Thiruchuli, Tamilnadu

● Asst.Manager, Kshema Power & Infrastructure Company Pvt Ltd. Kayathar.

May 2015 to Nov 2017

Tirunelveli, Tamilnadu.

● Sr.Engineer– Power Evacuation – Suzlon Power Infrastructure Ltd., January 2006 to Feb 2015 Devarkulam, Tirunelveli

RESUME TECHNICAL PROPOSAL

RESUME C.Kumaresan Page 2 of 3

● Project Engineer – Project Division – Indo Power Projects Ltd., April 2002 to March 2005 Kolkatta

● Electrical Supervisor – Project – Shree Abirami Engineering Works July 1999 to January 2002 Chennai

Employment Record

o Mar’2024 to Till now

Renfra Energy India Pvt Ltd

Erection, testing and commissioning of 110/33 kV Substation,33 kV OHL and 110 kV Transmission line projects Execution.

January 2022 to Feb’2024

JSW Energy Ltd (HINPA Incorporation) 930 MW Wind Farm Projects of Electrical 230kVSubstation, 230kV EHV line installation and 33kV OHL. Erection at SECI-IX,SECI-X Kayathar,Vilathilulam area Tuticorin Districts.

Jan 2020 to Dec 2021 M/S SRS Engineering Enterprises., Tirunelveli, Tamilnadu Supply,Erection,Testing and Commissioning of Power Transformers execution and maintenance. projects

Dec 2017 to Dec 2019 M/s PRV Constructions Pvt. Ltd, Thiruchuli, Tamilnadu. Supply, Erection, Testing and Commissioning, Maintenance of 110/33 kV Jakson NLC Solar Substation, Thiruchuli, Tamilnadu.

Supply, Erection, Testing and Commissioning, Maintenance of 110/11 kV Tidel Park Solar Substation, Mariyur, Tamilnadu.

May 2015 to Nov 2017 M/s. Kshema Power & Infrastructure Company Pvt Ltd, Kayathar,Tamilnadu. Supply, Erection, Testing and Commissioning, Maintenance of 230/33 kV,110/33-11 KV Sankaraperi,Kayathar Substation.0

January 2006 to Feb 2015 M/s.Suzlon Power Infrastructure Ltd.

● Preparation of BOQ/BOM

● Erection of Power Transformer with allied Substation equipment’s and Switchgears.

● Witness of Testing and Pre-Commissioning of Power Transformer, Current Transformer, Voltage Transformer, Breaker, Isolator and Control and Relay Panels in Substation.

● Erection of 230 KV and 110 KV Substation equipments like 50 MVA / 25 MVA Power Transformers, CT, CVT, SF6 Circuit breakers, Control and Relay Panel, Battery, Battery Charger.

RESUME TECHNICAL PROPOSAL

RESUME C.Kumaresan Page 3 of 3

● Construction of Civil-Foundation Like 50 MVA /25 MVA Power TRANSFORMER, 110/33 KV Pole Structures, 110kV, 33 KV Isolators,SF6 Gas Circuit Breaker, CT, PT, LAS, Cable Trenches, Yard leveling and Marking.

Projects Handled:

● KEELAVEERANAM 110/33 KV TNEB Substation.

● UTHUMALAI 110/33 KV TNEB Sub-station.

● SUNDANKURICHI 110/33 KV TNEB Sub-station.

● VEERASIGAMANI 110/33 KV TNEB Sub-station.

● RASTHA 110/33 KV TNEB Sub-station.

● UDAYATHUR 230/33 KV TNEB Sub-station.

● AMUTHAPURAM 230/33 KV TNEB Sub-station.

● SAMUGARENGAPURAM 110/33 KV TNEB Sub-station.

April 2002 to March 2005 Project Engineer – Project Division – Indo Power Projects Ltd.,

Erection, Testing & Commissioning of 400 KV Switchyard, Erection of 315 MVA Transformers, 50MVAR Shunt Reactors, 145 KV Neutral Grounding Reactors, 220/400 KV Towers, Beams, Stringing, 400/220 KV Electrical Sub-Station Equipments CT, CVT, ISOLATOR, SF6 GAS CIRCUIT BREAKER, WAVE TRAP, BP INSULATOR, 400/220 KV CONTROL & RELAY PANEL, 50V&220V Battery Bank Erection &Charging

(Worked in Jodhpur BHEL from RRVPNL,Rajasthan & Talaguppa BHEL from KPTCL, Karnataka)

July 1999 to January 2002 - Electrical Supervisor – Project – Shree Abirami Engineering Works, Chennai.

● Erection, Testing & Commissioning of 16MVA, BHEL make Transformers at TNEB Certification: