CURT WEIMER
ad782m@r.postjobfree.com
SUMMARY
Active Inspector since 2009, construction manager with a 25 year record of success and experience overseeing all phases of multimillion dollar construction, infrastructure, mechanical and utility system projects for private sector clients with a strong history of on-time/on-budget/high-quality project completions. AREAS OF QUALIFICATIONS
• OSHA 510 / OHSA 30hr
• AWS-CWI – #18031411 – renewal 2024
• API-1169 – #67558 – renewal 2025
• NACE CIP 1 – ID # 965233
• Proficient in Xcel, Word and Outlook -- QA/QC-Field Management – Blue Beam Weld Mapping – DOT - PHMSA Regulation Management -- Abnormal Operating Conditions -- Line Excavation and Backfill -- Line Locating -- Coating/Corrosion/Cathodic protection -- Change Order Management WORK HISTORY
Window Genie S Katy and N Richmond 6/23 -- Current
• General Manager
• Managed employees and daily operations.
• Advertising campaigns and Marketing
Cross Point Testing and Inspection Services, LLC 2/23 – 6/23
• AWS-CWI Weld Mapping and tracking welds made on daily basis. GIFS – Gulf Run Trunkline Meter Station / ETC 8/22 – 1/23
• AWS-CWI Weld mapping with Blue Beam
• NDT Management
• 1169 Certificate Recognized
GIFS – Gulf Run Pipeline / Enable Midstream Partners 3/22 – 8/22
• NDT Management for Tie In Crews
• AWS-CWI with Tie in Crews
• 1169 Certificate Recognized
QCS Onshore – Crystal Falls Aftercooler Repair / Trans Canada 9/21 – 10/21
• AWS-CWI of record on project
• 1169 Certificate Recognized
• NACE CIP 1 Certificate Recognized
QCS Onshore – Mathias Class Change / Trans Canada 6/21 – 9/21
• AWS-CWI of record on project
• 1169 Certificate Recognized
• NACE CIP 1 Certificate Recognize
QCS Onshore – Niles Indeck Meter Assembly / Trans Canada 3/21 – 6/21
• AWS-CWI of record on project
• 1169 Certificate Recognized
• NACE CIP 1 Certificate Recognized
QCS Onshore – 22” / 30” ANR Lines Relocation / Trans Canada 8/20 – 11/20
• AWS-CWI Coordinated w/ Sr CWI/Chief and contractor to complete project.
• 1169 Certificate Recognized
BWS Inspection – DCP AWS/CWI Centana Relocation Project 3/20 – 7/20
• AWS-CWI
• 1169 Certificate Recognized
Applied Consultants – ETC -- Lonestar Express II 8/19 – 12/19
• Environmental Inspector – multiple challenges on a fast paced project
• 1169 Certificate Recognized
BWS Inspection – ETC Abilene Airport HDD 2/19 – 7/19
• AWS-CWI Bore completed within limits set by Company
• 1169 Certificate Recognized
Liberty Energy Services – Kinder Morgan Station 301 – 5/18 – 11/18
• AWS-CWI – Completed compressor build out
• 1169 Certificate Recognized
Liberty Energy Services – Valley Crossing Pipeline – 5/17 – 2/18 RCI Group/TUV/SUD – Chevron Palo Co-lay Project – 8/16 – 4/17 CAREER HIGHLIGHTS -- EXPERIENCE
AWS-CWI, CIP 1, Chief Inspector, Utility, Environmental
• Environmental experience on a fast paced project that was completed on time, within budget, and with a multitude of environmental challenges..
• CWI/NACE 1 - Multiple projects
• Complete Team Management Skills – Interaction with Construction Foremen/Managers/Project design review team
• Managed fixed cost projects as well as T&M projects; capable of managing multiple projects at one time.
• Chief Inspector - Storage Tank Build out -- API 653
• Chief Inspector - Pipelines and Compressor Buildouts as well as in plant management experience.
• Utility Inspector - Civil Inspection - Grading and Concrete REFERENCES AND ADDITIONAL WORK HISTORY
• Available upon request.