To whom it concerns;
I have attached my resume for the position of Project Manager Heavy Highway
Transportation.
My background is extensive in state highway construction projects up to
$200 million in project size - cost control, budgets, negotiating with
owners, and providing cost for change orders, CPM schedule development and
monthly monitoring, project forecasting, managing subcontractors,
purchasing materials, form and false work design, quality control,
monitoring the Little Miller Act with respect to subcontractors, vendors
and purchase agreements.
It would be my pleasure to sit down with you and discuss, in detail, how I
can integrate beneficially into your organization. I am available to meet
at your earliest convenience.
Mr. Steve Basila 602-***-****) and Mr. Rick Shelley 602-***-****) will be
more than than happy to provide references.
Sincerely,
Jerry Koch
Jerry Koch
Project Manager
accat3@r.postjobfree.com
Enthusiastic about taking a set of plans and seeing the development into a
life size model, thrive on challenges, problem solving, looking for new
approaches and thinking outside of the box. Always looking for new
advantages, trying to foresee new opportunities and working with the owner
and designers for different angles to situations that allow them to have
the product they envisioned and ways to reduce time and cost. My
philosophy has always been that I need to find new avenues, within the
contract, that will reduce cost and will pay for my project cost.
I have a BS in Construction Engineering from Cal Poly, San Luis Obispo, CA;
AS degrees in Mathematics and Physics, AA degree in Architectural
Technology and I hold a E.I.T. license in California.
As part of the Red Mountain Power Road - University Drive team we received
the 2008 AGC Build Arizona Award and the 2009 Marvin M. Black Excellence in
Partnering "Special Recognition" Award.
Since October 2010 I have been working for Lawrence Construction
Projects:
MCDOT Northern Parkway Project, Dysart Road to Sarival Avenue
(10/2010 - Present)
Project Manager: Developed the CPM schedule, including direction, path and
relationships. Coordinated with the superintendent's daily about progress,
direction, schedule, man-power and equipment utilization. Worked closely
with the Resident Engineer about design issues; addressing conflicts,
interputation of design and possible changes for the ease of construction.
Developed cost analyses for the various change orders throughout the
project. Scheduled subcontractors for the project and provided direction
on their work to coincide with our work direction. Reviewed monthly
progress pay estimate and completed subcontractor's pay estimates.
This project consisted of 1.2 million cubic yards of excavation which
included 600,000 cubic yards of borrow. Along with the construction of two
single span bridges over the BNSF Rail Road, two double span bridges over a
city street and the construction of 4.5 miles of concrete lined channel and
seven box culverts. Trimming subgrade, ABC placement and trimming with
final PCCP on mainline and ramps, with asphalt paving on the four cross
roads. Staff on the project was a Project Engineer, General Field
Superintendent, Dirt Superintendents, Pipe superintendents, 2-structure
Superintendents and a Concrete Superintendent; along with myself.
For the past 16 years I worked for Pulice Construction, Inc. Phoenix,
Arizona
Projects:
ADOT Casa Grande-Tucson Highway (I-10), Twin Peaks Traffic Interchange:
($50.4m)
(5/2009 - 1/2011)
Project Manager: Developed the CPM schedule, including direction, path and
relationships. Managed day to day construction progress, reviewed weekly,
superintendents' progress, and manpower and equipment utilization. Worked
with designers and owners to interpret the intent of design and made
recommendations for adjustments to better the schedule and for ease of
construction. Developed VE's to eliminate detours that benefited the
owners and local public. Developed cost analyses for the various change
orders throughout the project; one in the amount of $1.9m. Various change
orders I worked with the designers to provide faster construction times and
to reduce the cost. Developed cost for the various critical activities and
compared them to the bid budget, attempting to find an alternate method
that was cheaper and faster that fit the changing conditions. Set up and
maintained on site purchasing of materials and approved purchase orders and
invoices.
This project was a 515 calendar day project and time started from the date
of the letter to award to have the project opened to traffic. This project
was completed on time and at projected margin; that included $1.9m in
change orders and $1.4m in increased item of work. Staff on the project
was a Project Engineer, Office Administrator, General Field Superintendent,
2-Dirt Superintendents, 2-Pipe superintendents, 3-structure Superintendents
and a Concrete Superintendent; along with myself. At the peak of
construction we had over 100 craft personnel on site.
This project included 2-700' I-girder bridges across the Santa Cruz River,
one 2 span I-girder bridge across interstate I-10 and a box girder bridge
across the Union Pacific Railroad main track East to West Coast. Soil
cement bank reconstruction, 404 mitigation area and reconstruction, 45,000
lf of various storm drain, 5200 lf of 24" DIP installation including 2 jack
and bore locations one being 800 lf. Dirt on site was 350,000 cy and
import of 700,000 cy from a local commercial pit which required that we
become MSHA certified with our own pit license. Paving both AC and PCCP
were a part of this project including the 1-1/2" mill and overlay of 5
miles of existing city streets 4 lanes wide which was accomplished in 6
working days.
As Project Manager I started this project and saw it through to final
acceptance and opening to traffic. This included completion of all punch
lists. This project was completed on time and at projected budget.
ADOT Price Freeway (SR Loop 101) from Red Mountain Freeway (SR 202) to
Santan Freeway (SR 202) 10 miles of HOV Lanes (7/2008 - 5/2009) ($21.0 Mil)
Project Manager: Developed the CPM schedule along with the necessary
relationships. Provided cost analysis for various change orders. Worked
with ADOT to revise and develop a method to divide the project into three
sections rather two, this helped with the continuity of manpower and
equipment. Plans required that all irrigation lines and controller wires
be removed from the freeway median, connect the existing sleeves together
and rerun new irrigation and controller wires. ADOT was concerned with
everything going back in like condition and with proper points of
connection. Developed a VE that provided a split 12" corrugated sleeve,
this eliminated the disruption to the irrigation, allowed the work to
accelerate and was a savings to everyone. Material on site at specific
sections was determined to be unsuitable; we tested the material at those
locations and provided test results that showed two sections were
acceptable. This turned into a VE to leave the material in place, reduced
haul off and import of new material and rebalancing the earthwork was part
of the VE. Plans called for the total removal of asphalt that was the
original PCCP track grade another VE was submitted to reduce the PCCP
structural section in several areas and leaving the AC in place, this
reduced the AC requirements and haul off. We tested the existing AB Class
II and determined that we could salvage enough material to use at the
required locations and therefore none was ever purchased. Worked with our
equipment department to modify and curb mold for a slip form paver to
increase the bridge barrier by and additional 10", from 32" to 42". Hand
pouring of the 10" barrier increase was not an option due to having 7000 lf
to accomplish
This project consisted of 9.75 miles of HOV lanes, new medium lighting,
medium barrier, PCCP paving and AR-ACFC overlay, removals and medium bridge
barrier height increase by adding 10" to existing. Furnishing new and the
reconstruction of existing sign structures, including the reconstruction of
existing sign foundations, new foundations and removal of existing. New
traffic loops and relocation of fiber optic cable.
I started this project and then relocated to the Twin Peaks T.I.
Interchange Project.
ADOT Red Mountain Freeway (SR Loop 202, Power Road to University Drive
(1/2005 - 7/2008) ($195.0 Mil)
Project Manager Structural Concrete: Construction of 4.83 miles of urban
freeway that included 16 bridges, 500,000 square feet of a combination of
MSE, Structural Concrete and Masonry sound walls, the removal of 3 bridges
across the Central Arizona Project, one storm water pumping station, sheet
piling and the demolition and reconstruction of a new outfall structure
through the Maricopa Flood Control's Spook Hill Dam.
I provided the CPM scheduling for all the structural concrete, provided
cost analysis for proposed changes and worked with the designer and ADOT on
a VE to eliminate the structural concrete sound walls on a bridge with
replacement with masonry walls.
Established the methodology to remove three CAP Canal bridges sequence of
work and necessary equipment and oversaw the work. Designed and oversaw
the construction of wood barges to be placed under the bridges to be
removed, monitored the daily progress of removal. The removal was to
remove the deck in specific areas to allow for existing water lines that
were under the deck to be removed from the top, then saw cut the bridge
between the girders, diaphragms and abutment and remove each section using
up to as many as three cranes having to transfer the load between cranes.
Determining the weight of each piece and then working with the crane
company designing the radius of pick and transfer of load points, size of
cranes of their locations during the removal process.
Of all the bridges we constructed, 8 each were over the CAP Canal and
worked closely with the daily CAP inspection and safety using the Bureau of
Reclamation safety guidelines and policies. The CAP has now adapted this
bridge removal procedure that was developed and is now a standard guideline
for bridge removal. I also oversaw the onsite fabrication of span girder
plys (28 each 92' long by 10' high and only 1' thick), designed the method
for picking, moving and erecting the plys at four locations that spanned
the CAP Canal for two 900 foot bridges. Contracted with a consultant
designer, to designing a haul road bridge across the CAP Canal, including
the installation and removal by our own work forces.
When we were about half way through the project, the Project Manager was
relocated to a new project and I assumed the position as full Project
Manager. It was at that point that I had to finish the Maricopa Flood
Control District 1st dam rehabilitation, consisting of a new core 30' deep
and 30" wide. Completed the earthwork and balancing of the 4 miles of
their flood pools, install sheet piling, originally 2 phases but realigned
to eliminate one phase, remove the outfall structure, construct a new
structure and replace the dam. I finalized the project including the final
stages of PCCP and the application of AR_ACFC, roadway lighting, signing
and striping. Working with the Department and a new fabricator, we
designed and submitted a system of lightweight sound panels to be installed
on a 900 lf bridge, which included several changes for the structural
support system.
Completed all punch lists and opened the project to traffic, finalized the
last pay estimate with ADOT, closed out all ADOT paper work including
change orders and received their final acceptance letter. Finalized all
subcontractors final pay estimates, made sure that all necessary project
paper work was archived and demobilized the project. This project was
completed ahead of schedule and under budget.
ADOT Santan Freeway (SR 202), Arizona Avenue to Gilbert Road
(12/2003 - 1/2005)
Project Manager Structural Concrete: Developed the structural concrete CPM
for the 7 bridges, 3 were over a UPRR line and over a SRP Canal, 250,000
square feet of concrete retaining walls and MSE Walls, a storm water pump
station and channel lining. Redesigned the various retaining walls;
changing the heights of the retaining walls, to remove steps in the
footings and to level out the wall tops to take advantage of a constant
form height. Contracted with a consultant designer, to designing a haul
road bridge across the SRP Canal, including the installation and removal by
our own work forces.
About half way through this project the Project Manager was reassigned and
I assumed that role. Completing the final mass excavation, sub-grade, base
AC, PCCP, AR-ACFC, freeway signing and electrical.
Completed all punch lists and opened the project to traffic, finalized the
last pay estimate with ADOT, closed out all ADOT paper work including
change orders and received their final acceptance letter. Finalized all
subcontractors final pay estimates, made sure that all necessary project
paper work was archived and demobilized the project. This project was
completed ahead of schedule and under budget.
ADOT I-10 / I-19 Traffic Interchange, Tucson, AZ
(5/2002 - 12/2003)
Project Manager Structural Concrete: Developed the project CPM schedule,
coordinated the construction of 10 cast in place box girder bridges,
retaining walls along with various other minor box culverts and other
miscellaneous structures. Developed the girder camber build up for the
various spans of each bridge and worked with the excavation superintendent
for the construction of soffet fills for some of the structures.
Coordinated with the various inspectors and Resident Engineer on various
issues, provided cost analysis for various change order that related to
project, monitored weekly cost and held on site meeting with the various
superintendents to review manpower and equipment requirements to meet the
schedule, and advise them of future issues and constant changes of
earthwork haul patterns.
Once we were 90% complete with the structural work I was transferred to
another project. This was an A + B Project where we bid to reduce the
contract time to 758 working days from 910 days; this project was completed
on time and under budget.
ADOT Red Mountain Freeway (SR Loop 202), Gilbert Road to Higley Road
Project Manager Structural Concrete: Scheduled the construction and
developed the CPM for the construction of 5 box girder bridges, several box
culverts, and multiple cast- in-place retaining walls. Working with the
owner and designer on the relocation of freeway ramps, developed a VE to
reducing the size of retaining walls creating a 3:1 slope and project
savings. Resized various retaining wall heights; making them more
efficient for construction and reducing their cost. Contracted with a
consultant designer, to designing a 2-span temporary haul road bridge
across the SRP Canal, including the installation and removal by our own
work forces.
ADOT Red Mountain Freeway (SR Loop 202), Country Club Drive to Gilbert
Road, Phase "B"
Project Manager Structural Concrete: The construction of a single bridge
and an equipment underpass box culvert, existing street improvements.
ADOT Red Mountain Freeway (SR Loop 202), Country Club Drive to Gilbert
Road, Phase "A"
Project Manager Structural Concrete: Developed the project CPM that
consisted of the construction of 3.3 miles of urban divided freeway. This
project had 7 bridges; 3 were I-girders and 4 were box girder bridges;
sewage pumping station and storm water pump station, concrete box culvert
and equipment underpass and 200,000 square feet of cast-in-place concrete
sound walls and MSE Walls.
ADOT Red Mountain Freeway (SR Loop 202), McKellips Road to Country Club
Drive
Project Manager: Project consisted of construction of one box girder
bridge, 25,000 square feet of MSE walls, grading, storm drainage, PCCP
Paving, reconstruction of a 4 lane city street and mud jacking of several
approached to bridges. Developed a plan to provide a detour behind the box
girder bridge eliminating the need for traffic restrictions and allowing
the bridge to be construction on a soffet fill rather than falsework,
secured a
permit from the Salt River Gila Indian Reservation, to cross their property
with this detour.
During excavation and waste haul off we discover virgin aggregate deposits,
which we crushed for structural backfill and ABC Class II aggregates. Due
to the volume of material, we supplied another Pulice project with backfill
material and they delivered over excavated material, double haul, to help
fill the void from crushing and eliminated the waste haul.
ADOT Red Mountain Freeway (SR Loop 202), Dobson Road to Alma School Road
Project Manager Structural Concrete: Project consisted of construction of
one box Girder Bridge and one I-Girder Bridge and 50,000 square feet of MSE
Wall; which was cast on site, one 42' x 14' equipment underpass and 100,000
cubic yards of soil cement ban protection. Developed a VE to redesign a
section of the soil cement from a slurry benoite construction to a
conventional cast in place construction method this was accomplished by
relocating of two existing crushing slurry ponds.
After 6 months on this project the Project Manager was moved to another
project and I assumed the position of Project Manager.
Completed the project including all punch lists and opened the project to
traffic, finalized the last pay estimate with ADOT, closed out all ADOT
paper work including change orders and received their final acceptance
letter. Finalized all subcontractors final pay estimates, made sure that
all necessary project paper work was archived and demobilized the project.
This project was completed ahead of schedule and under budget.
ADOT Squaw Peak Freeway (SR 51) Shea Boulevard Road
Project Manager: This project included the construction of an urban winged
traffic interchange and bridge. The bridge foundation was to be
constructed partially on caissons and balance on a spread footing on rock.
The rock was very solid and required drilling and shooting the rock in a
close proximity to local traffic and businesses, developed and plan for the
daily activity of blasting and monitoring local business for seismic
disturbance in accordance with local codes. Designed a steel beam and Geo
Fabric retaining wall, to retain a detour thus eliminated the need for two
phase construction of this bridge.
The bridge was a post tension structure but the ramp wings were
conventional construction. The designer had a requirement that columns of
dead weight be constructed to preload the post tension bridge to reduce the
up ward deflection and that would mimic the wing loading. Developed a plan
using concrete barrier as a dead load which providing a better load
distribution across the structure and reducing bridge upward deflection.
Completed the project including all punch lists and opened the project to
traffic, finalized the last pay estimate with ADOT, closed out all ADOT
paper work including change orders and received their final acceptance
letter. Finalized all subcontractors final pay estimates, made sure that
all necessary project paper work was archived and demobilized the project.
This project was completed on of schedule.